Approval rates for renewable energy planning applications
Approved means the project got planning permission at some stage (by the council, on appeal or from the Secretary of State or Scottish Ministers), including projects that have since been built or lapsed. Refused means the latest decision was a refusal. Withdrawn applications aren't decisions, so they're shown separately.
Approval rate of decided applications
| Technology | Approved | Refused | Approval rate | Median days to decision | Withdrawn | Awaiting decision |
|---|---|---|---|---|---|---|
| Battery storage | 1,796 | 175 | 91% | 196 | 116 | 464 |
| Solar PV | 6,094 | 404 | 94% | 74 | 197 | 622 |
| Onshore wind | 1,391 | 594 | 70% | 462 | 315 | 287 |
| Offshore wind | 90 | 3 | 97% | 590 | 3 | 13 |
Approval rates by nation
| Technology | Nation | Approved | Refused | Approval rate |
|---|---|---|---|---|
| Battery storage | England | 1,319 | 129 | 91% |
| Battery storage | Scotland | 338 | 35 | 91% |
| Battery storage | Wales | 107 | 10 | 91% |
| Battery storage | Northern Ireland | 32 | 1 | 97% |
| Solar PV | England | 5,343 | 373 | 93% |
| Solar PV | Scotland | 410 | 12 | 97% |
| Solar PV | Wales | 293 | 17 | 95% |
| Solar PV | Northern Ireland | 47 | 2 | 96% |
| Onshore wind | England | 405 | 231 | 64% |
| Onshore wind | Scotland | 645 | 274 | 70% |
| Onshore wind | Wales | 112 | 58 | 66% |
| Onshore wind | Northern Ireland | 229 | 31 | 88% |
| Offshore wind | Offshore | 89 | 3 | 97% |
Only combinations with at least 10 decided applications are shown.
How long decisions take
Days from the planning application date to the permission or refusal date in the REPD, median across 10,660 applications with both dates. Large schemes decided nationally (NSIPs in England and Wales, section 36 in Scotland) take much longer than council decisions, and rooftop solar much less.
Planning applications submitted each year
| Year | Battery storage | Solar PV | Onshore wind | Offshore wind |
|---|---|---|---|---|
| 2021 | 241 | 480 | 68 | 2 |
| 2022 | 332 | 969 | 68 | 6 |
| 2023 | 395 | 1,259 | 123 | 4 |
| 2024 | 546 | 1,009 | 115 | 15 |
| 2025 | 591 | 1,092 | 140 | 3 |
| 2026 (to Sept) | 193 | 594 | 64 | 7 |
Applications awaiting a decision
1,386 battery, solar and wind applications are waiting for a decision. The planning authorities with the most:
| # | Planning authority | Awaiting decision |
|---|---|---|
| 1 | Scottish Government (S36) | 204 |
| 2 | North Yorkshire | 32 |
| 3 | The Planning Inspectorate - National Infrastructure | 27 |
| 4 | Welsh Government (NSIP) | 27 |
| 5 | North Northamptonshire | 23 |
| 6 | Aberdeenshire | 23 |
| 7 | Derry City and Strabane | 22 |
| 8 | Highland | 20 |
| 9 | West Northamptonshire | 17 |
| 10 | County Durham | 16 |
Planning authorities with the most applications
All applications in the database, whatever their outcome, by technology (top five authorities each):
| Technology | Planning authorities (applications) |
|---|---|
| Battery storage | Scottish Government (S36) (232); North Yorkshire (49); Highland (47); Wiltshire (43); Milton Keynes (40) |
| Solar PV | Somerset (176); Cornwall (175); North Yorkshire (139); Wiltshire (129); Dorset (118) |
| Onshore wind | Scottish Government (S36) (343); Aberdeenshire (179); Highland (135); Dumfries and Galloway (98); Fermanagh and Omagh (94) |
| Offshore wind | DECC (S36) (35); The Planning Inspectorate - National Infrastructure (33); Marine Scotland (31); Scottish Government (S36) (7); Marine Management Organisation (3) |
Appeals
223 projects in the database have appeal granted as their latest planning status and 301 appeal refused. The list gives the appeal reference and dates for each.
Questions about renewable energy planning applications
What share of renewable energy planning applications are approved?
In the Renewable Energy Planning Database (13 November 2026 release), 89% of decided battery, solar and wind applications were approved: battery storage 91%, solar 94%, onshore wind 70% and offshore wind 97%. Withdrawn applications aren't counted as decided.
How long does a renewable energy planning application take?
The median time from application to decision was 196 days for battery storage, 74 days for solar and 462 days for onshore wind, using the submitted and decision dates in the REPD.
Which council has the most renewable energy planning applications waiting?
Scottish Government (S36) has the most battery, solar and wind applications awaiting a decision (204).
How many renewable projects win on appeal?
The REPD records 223 projects whose latest status is appeal granted and 301 appeal refused across battery, solar and wind.
Get the data
Battery, solar and wind list + quarterly updates
£1,195 a year
+ VAT (£1,434) a year
- The full UK battery, solar and wind list now (Excel + CSV)
- 4 quarterly updates over the year
- A changes file each quarter: new projects and status changes
- Change vs last refresh column in every file
For £400 more than the one-off list you get the next four quarterly editions, each with a changes file. Renews yearly; cancel any time and keep the files you have had.
UK battery, solar and wind project list
£795
+ VAT (£954), one-off
- Every UK battery, solar and wind project (Excel + CSV)
- Capacity, status, planning dates, grid connection
- Developer company, Companies House details and parent company
One edition, dated 26 November 2026. No updates.
13,283 projects in the current edition. Pay by card through Stripe. Your files are emailed as a zip (Excel and CSV) within 15 minutes between 7am and 10pm; overnight orders arrive by 7:15am. Prices are plus VAT, which is added at checkout. You get a VAT receipt. For business buyers only; licensed for use in your own business.
See real rows in the free sample (directors' names removed).
Only need one technology, or just the live pipeline? Buy a pack: Battery storage 2,756 projects, £165; Solar farm 7,640 projects, £458; Wind farm 2,887 projects, £173; pipeline (consented and under construction) 6,380 projects, £479 (+ VAT, one-off). See the packs.