Biomass power stations by status
Dedicated biomass plants burn wood chip, pellets, straw or waste wood to make electricity; co-firing burns biomass in a converted coal station. 81 dedicated biomass and 2 co-firing projects are operating. The pipeline is 76 projects (167 MW).
| Status | Projects | MW |
|---|---|---|
| Operational | 83 | 4,129 |
| Under construction | 8 | 81 |
| Consented, not yet built | 68 | 87 |
| Awaiting decision | 2 | 267 |
| Refused | 19 | 317 |
| Withdrawn | 22 | 768 |
| Permission expired | 13 | 981 |
| Abandoned | 63 | 2,992 |
| Revised (re-applied) | 10 | 177 |
| Decommissioned | 2 | 775 |
| All | 290 | 10,575 |
Biomass power stations by region
Yorkshire and The Humber has the most operating biomass capacity (2,769 MW).
Operational biomass MW by region
| Region | Biomass projects | Operational | Operational MW | Consented or building | Pipeline MW | Awaiting decision |
|---|---|---|---|---|---|---|
| North East | 15 | 4 | 501 | 3 | 106 | 0 |
| North West | 19 | 5 | 120 | 5 | 3 | 0 |
| Yorkshire & Humber | 46 | 16 | 2,769 | 11 | 31 | 0 |
| East Midlands | 31 | 8 | 98 | 13 | 10 | 0 |
| West Midlands | 23 | 4 | 8 | 5 | 1 | 0 |
| East of England | 22 | 8 | 203 | 4 | 2 | 0 |
| London | 6 | 4 | 32 | 1 | 0 | 0 |
| South East | 11 | 3 | 42 | 2 | 0 | 0 |
| South West | 27 | 5 | 10 | 9 | 6 | 0 |
| Scotland | 50 | 16 | 238 | 14 | 4 | 2 |
| Wales | 34 | 7 | 88 | 9 | 3 | 0 |
| Northern Ireland | 6 | 3 | 20 | 0 | 0 | 0 |
Biomass plants by size
Most biomass plants are small: the median operating project is 9.0 MW, and 42 of 83 are under 10 MW. A handful of large stations hold most of the megawatts.
Operational biomass plants by capacity
Largest biomass power stations in the UK
The ten largest operating biomass projects by capacity:
| Site | Operator company | Region | Status | MW |
|---|---|---|---|---|
| Drax Biomass Power Station - Unit 1 | DRAX POWER LIMITED | Yorkshire & Humber | Operational | 645.0 |
| Drax Biomass Power Station - Unit 2 | DRAX POWER LIMITED | Yorkshire & Humber | Operational | 645.0 |
| Drax Biomass Power Station - Unit 3 | DRAX POWER LIMITED | Yorkshire & Humber | Operational | 645.0 |
| Drax Biomass Power Station - Unit 4 | DRAX POWER LIMITED | Yorkshire & Humber | Operational | 645.0 |
| Lynemouth Power Station | Not matched | North East | Operational | 420.0 |
| Markinch Biomass CHP Plant | Not matched | Scotland | Operational | 65.0 |
| Stevens Croft | Not matched | Scotland | Operational | 50.4 |
| Iggesund Paperboard CHP Plant | Not matched | North West | Operational | 49.0 |
| Snetterton Biomass Plant | Not matched | East of England | Operational | 44.2 |
| Tilbury Green Power | TILBURY GREEN POWER LIMITED | East of England | Operational | 43.0 |
And the largest consented or under construction:
| Site | Operator company | Region | Status | MW |
|---|---|---|---|---|
| Billingham Biomass Power Station | Not matched | North East | Consented, not yet built | 49.8 |
| Port Clarence Biomass Plant | Not matched | North East | Under construction | 40.0 |
| Gameslack Farm | Not matched | Yorkshire & Humber | Under construction | 17.5 |
| Simpsons Malt Limited Biomass | SIMPSONS MALT LIMITED | North East | Under construction | 16.0 |
| Yorkshire Botanicals - Biomass Boiler | YORKSHIRE BOTANICALS LIMITED | Yorkshire & Humber | Consented, not yet built | 5.0 |
| Yorkshire Grown Produce, Main Road - Biomass Boiler | YORKSHIRE GROWN PRODUCE LIMITED | Yorkshire & Humber | Consented, not yet built | 4.0 |
| Framptons Limited Energy Centre | FRAMPTONS LIMITED | South West | Under construction | 3.9 |
| Raventhorpe Nursery, Rootas Lane - Biomass Boiler | RAVENTHORPE NURSERY LIMITED | Yorkshire & Humber | Consented, not yet built | 2.0 |
| Brampton Road, Longtown - Biomass Boilers | EVENWOOD PRODUCTS LIMITED | North West | Consented, not yet built | 1.8 |
| Barn Farm Lowfields, Navenby - Biomass boiler | G.E. PORTER & SONS LIMITED | East Midlands | Consented, not yet built | 1.6 |
Biomass combined heat and power
42 of the 83 operating biomass projects are recorded as CHP, selling heat to a site or a heat network as well as power. Across every status, 93 biomass projects are CHP.
Biomass output
35 operating biomass plants are matched to Ofgem's Renewables Obligation register, with the electricity they were issued certificates for between April 2025 and March 2026: 4.7 million MWh in total. 4 biomass projects hold or held a CfD.
Biomass operators
The companies with the most biomass projects in the list, by Companies House name:
| # | Company (Companies House name) | Projects |
|---|---|---|
| 1 | G.E. PORTER & SONS LIMITED | 4 |
| 2 | DRAX POWER LIMITED | 4 |
| 3 | SPEP LIMITED | 3 |
| 4 | ECO2 LIMITED | 2 |
| 5 | SIMPSONS MALT LIMITED | 2 |
| 6 | S P & G BLYTHING LIMITED | 2 |
| 7 | CLIMATE CORPORATE ADVISORY SERVICES LLP | 1 |
| 8 | SCOTTS OF THRAPSTON LIMITED | 1 |
| 9 | FACCENDA PROPERTY LIMITED | 1 |
| 10 | R.G. SIMPSON LIMITED | 1 |
Questions about biomass power stations
How many biomass power stations are there in the UK?
The Renewable Energy Planning Database (release of 13 November 2026) lists 83 operating biomass power projects (81 dedicated biomass, 2 co-firing) with 4,129 MW between them, plus 76 consented or under construction.
What is the largest biomass power station in the UK?
Drax Biomass Power Station - Unit 1 is the largest operating biomass unit in the list at 645 MW. Drax's converted coal units dominate UK biomass capacity.
Where are the UK's biomass power stations?
Yorkshire and The Humber has the most operating biomass capacity: 2,769 MW across 16 plants.
How big is a typical biomass plant?
Most are small: 42 of the 83 operating biomass projects are under 10 MW and the median is 9.0 MW. A few very large stations hold most of the capacity.
How many biomass projects never get built?
Many. 129 biomass projects in the database were refused, withdrawn, abandoned, decommissioned or let their permission lapse, against 83 operating. Of decided applications, 91% were approved.
Get the biomass list
The biomass power stations pack has all 290 of these projects, every status, for £145 + VAT (£174), one-off. Buy the pack, or get the full list of every type:
Energy from waste and biomass list + quarterly updates
£549 a year
+ VAT (£658.80) a year
- The full UK energy from waste and biomass list now (Excel + CSV)
- 4 quarterly updates over the year
- A changes file each quarter: new projects and status changes
- Change vs last refresh column in every file
For £154 more than the one-off list you get the next four quarterly editions, each with a changes file. Renews yearly; cancel any time and keep the files you have had.
UK energy from waste and biomass plant list
£395
+ VAT (£474), one-off
- Every UK energy from waste, biomass and landfill gas project (Excel + CSV)
- Capacity, CHP, status, planning dates, EA permit, Ofgem output
- Operator company, Companies House details and parent company
One edition, dated 27 November 2026. No updates.
936 projects in the current edition. Pay by card through Stripe. Your files are emailed as a zip (Excel and CSV) within 15 minutes between 7am and 10pm; overnight orders arrive by 7:15am. Prices are plus VAT, which is added at checkout. You get a VAT receipt. For business buyers only; licensed for use in your own business.