The renewable energy pipeline
The pipeline here means projects that have planning consent but haven't started building (5,978) and projects under construction (402). Solar has the most pipeline projects (4,377 of 6,380), but battery storage and offshore wind together hold 76% of the pipeline capacity (131.5 GW).
Pipeline projects by technology
- Battery storage1,526
- Solar PV4,377
- Onshore wind438
- Offshore wind39
| Technology | Consented, not built | MW | Under construction | MW |
|---|---|---|---|---|
| Battery storage | 1,400 | 79,763 | 126 | 10,591 |
| Solar PV | 4,146 | 28,821 | 231 | 3,656 |
| Onshore wind | 401 | 7,502 | 37 | 2,039 |
| Offshore wind | 31 | 29,327 | 8 | 11,845 |
New renewable energy projects by region
Offshore has the most capacity in the pipeline (41,072 MW).
| Region | Battery | Solar | Wind | All projects | MW |
|---|---|---|---|---|---|
| North East | 51 | 240 | 2 | 293 | 4,046 |
| North West | 123 | 435 | 8 | 566 | 8,768 |
| Yorkshire and The Humber | 126 | 467 | 38 | 631 | 17,322 |
| East Midlands | 139 | 449 | 4 | 592 | 19,810 |
| West Midlands | 130 | 433 | 1 | 564 | 6,695 |
| East of England | 187 | 496 | 8 | 691 | 12,290 |
| London | 7 | 223 | 2 | 232 | 465 |
| South East | 181 | 639 | 1 | 821 | 10,772 |
| South West | 157 | 518 | 16 | 691 | 7,866 |
| Scotland | 296 | 325 | 202 | 823 | 35,867 |
| Wales | 98 | 135 | 31 | 264 | 6,693 |
| Northern Ireland | 31 | 17 | 126 | 174 | 1,878 |
| Offshore | 0 | 0 | 38 | 38 | 41,072 |
New consents, construction starts and switch-ons each quarter
Projects granted planning consent in each of the last eight quarters (by the permission date in the REPD, whatever their status now), plus the projects that started construction and became operational. In 2026 Q3, 246 projects with 11,552 MW were consented. The most recent quarters tend to rise in later releases as the REPD catches up.
MW granted planning consent each quarter
| Quarter | Battery consents | Solar consents | Wind consents | MW consented | Construction starts | Became operational |
|---|---|---|---|---|---|---|
| 2024 Q4 | 77 | 201 | 12 | 6,438 | 13 | 15 |
| 2025 Q1 | 137 | 205 | 19 | 15,069 | 28 | 10 |
| 2025 Q2 | 126 | 224 | 21 | 13,576 | 23 | 11 |
| 2025 Q3 | 169 | 268 | 20 | 23,922 | 21 | 15 |
| 2025 Q4 | 83 | 203 | 33 | 7,405 | 18 | 12 |
| 2026 Q1 | 87 | 218 | 20 | 6,148 | 19 | 10 |
| 2026 Q2 | 78 | 201 | 16 | 10,689 | 16 | 14 |
| 2026 Q3 | 57 | 162 | 27 | 11,552 | 15 | 20 |
How old the consents are
2,360 of the consented projects not yet built got their consent three years ago or more. In England and Wales a planning permission normally has to be started within three years, though many are extended or kept alive with minimal works, so an old consent is a lead to check rather than a dead one.
Consented projects not yet built, by age of consent
Grid connection dates and CfD contracts
478 pipeline projects are matched to a grid register, 339 with a connection date (actual or contracted), and 270 hold a Contract for Difference. A CfD and a firm connection date are the strongest signs a consented project will actually be built.
Largest new renewable energy projects
The ten largest battery storage projects consented or under construction:
| Site | Operator company | Region | Status | MW |
|---|---|---|---|---|
| Thorpe Marsh Power Station - Battery Energy Storage | Not matched | Yorkshire & Humber | Consented, not yet built | 1,450.0 |
| Thorpe Marsh Power Station, Marsh Lane - Battery Energy Storage | Not matched | Yorkshire & Humber | Consented, not yet built | 1,400.0 |
| West Leake Lane, Ratcliffe - Battery Storage | SANDBROOK CAPITAL BES LTD | East Midlands | Consented, not yet built | 1,200.0 |
| Fairfields Energy Storage System | Not matched | East Midlands | Consented, not yet built | 1,025.0 |
| The Balk, Almholme - Energy Storage System | INNOVA RENEWABLES LIMITED | Yorkshire & Humber | Consented, not yet built | 1,025.0 |
| Swinford Battery Energy Storage System | NATPOWER UK LIMITED | East Midlands | Consented, not yet built | 1,000.0 |
| Tesside GigaPark - Battery Energy Storage System | NP SPV 27 LIMITED | North East | Consented, not yet built | 1,000.0 |
| Coalburn II Energy Storage Facility - Battery Storage Facility | Not matched | Scotland | Under construction | 1,000.0 |
| Rover Way, Splott - Energy Park & Data Centre | LATOS CARDIFF LTD | Wales | Consented, not yet built | 1,000.0 |
| Fanny House Farm, Bay Gateway - Battery Storage | INNOVA RENEWABLES LIMITED | North West | Consented, not yet built | 940.0 |
The ten largest solar projects consented or under construction:
| Site | Operator company | Region | Status | MW |
|---|---|---|---|---|
| Springwell, Lincoln - Springwell Solar Farm & Battery Storage | EDF ENERGY RENEWABLES LIMITED | East Midlands | Consented, not yet built | 800.0 |
| One Earth Solar Farm | Not matched | East Midlands | Consented, not yet built | 740.0 |
| Cottam Solar Project | ISLAND GREEN POWER UK LIMITED | East Midlands | Consented, not yet built | 600.0 |
| Gate Burton - Solar & Energy Storage Park | LOW CARBON LIMITED | East Midlands | Consented, not yet built | 531.0 |
| Green Hill Solar Farm & Battery Storage | ISLAND GREEN POWER UK LIMITED | East Midlands | Consented, not yet built | 500.0 |
| Heckington Fen Solar Park | ECOTRICITY LIMITED | East Midlands | Consented, not yet built | 500.0 |
| Tillbridge Solar Farm, Hemswell - Solar Panels | TILLBRIDGE SOLAR LIMITED | East Midlands | Consented, not yet built | 500.0 |
| Longfield | LONGFIELD SOLAR ENERGY FARM LIMITED | East of England | Consented, not yet built | 500.0 |
| Sunnica Energy Farm (East and West) | SUNNICA LIMITED | East of England | Consented, not yet built | 500.0 |
| West Burton Solar Project | ISLAND GREEN POWER UK LIMITED | East Midlands | Consented, not yet built | 480.0 |
Offshore wind projects consented or under construction:
| Site | Operator company | Region | Status | MW |
|---|---|---|---|---|
| Berwick Bank Offshore Wind Farm | Not matched | Offshore | Consented, not yet built | 4,100.0 |
| Hornsea 3 | Not matched | Offshore | Under construction | 2,955.0 |
| Dogger Bank A & B (was Creyke Beck A & B) | Not matched | Offshore | Under construction | 2,400.0 |
| Hornsea 4 | Not matched | Offshore | Consented, not yet built | 2,400.0 |
| West of Orkney Wind Farm | Not matched | Offshore | Consented, not yet built | 2,000.0 |
| Dogger Bank South East | Not matched | Offshore | Consented, not yet built | 1,500.0 |
| Dogger Bank South West | Not matched | Offshore | Consented, not yet built | 1,500.0 |
| Mona Offshore Wind Farm | Not matched | Offshore | Consented, not yet built | 1,500.0 |
| Morgan Offshore Wind Farm | Not matched | Offshore | Consented, not yet built | 1,500.0 |
| Outer Dowsing Offshore Wind Farm | Not matched | Offshore | Consented, not yet built | 1,500.0 |
Questions about new renewable energy projects
How many new renewable energy projects are planned in the UK?
6,380 battery storage, solar and wind projects of 150 kW or more are consented or under construction (173,544 MW), according to the Renewable Energy Planning Database release of 13 November 2026: 1,526 battery, 4,377 solar, 438 onshore wind and 39 offshore wind.
Which region has the most new renewable projects?
Offshore has the largest pipeline by capacity: 41,072 MW across 38 projects.
How much renewable capacity got planning consent in 2026 Q3?
246 battery, solar and wind projects with 11,552 MW were granted consent in 2026 Q3, by the permission dates in the REPD. Recent quarters can rise as the REPD catches up with decisions.
Do all consented projects get built?
No. 2,360 consented projects have had their consent for three years or more without starting construction; many are waiting for a grid connection, and some will lapse.
Get the pipeline
The pipeline pack has every battery, solar and wind project that is consented or under construction (6,380 projects) for £479 + VAT (£574.80), one-off. The annual plan tracks it every quarter with a changes file:
Battery, solar and wind list + quarterly updates
£1,195 a year
+ VAT (£1,434) a year
- The full UK battery, solar and wind list now (Excel + CSV)
- 4 quarterly updates over the year
- A changes file each quarter: new projects and status changes
- Change vs last refresh column in every file
For £400 more than the one-off list you get the next four quarterly editions, each with a changes file. Renews yearly; cancel any time and keep the files you have had.
UK battery, solar and wind project list
£795
+ VAT (£954), one-off
- Every UK battery, solar and wind project (Excel + CSV)
- Capacity, status, planning dates, grid connection
- Developer company, Companies House details and parent company
One edition, dated 26 November 2026. No updates.
13,283 projects in the current edition. Pay by card through Stripe. Your files are emailed as a zip (Excel and CSV) within 15 minutes between 7am and 10pm; overnight orders arrive by 7:15am. Prices are plus VAT, which is added at checkout. You get a VAT receipt. For business buyers only; licensed for use in your own business.
See real rows in the free sample (directors' names removed).
Only need one technology, or just the live pipeline? Buy a pack: Battery storage 2,756 projects, £165; Solar farm 7,640 projects, £458; Wind farm 2,887 projects, £173; pipeline (consented and under construction) 6,380 projects, £479 (+ VAT, one-off). See the packs.